Record an interior change as a decision with affected deliverables, not just a new image. Identify the approved baseline, the requested change and every plan, schedule, budget and order that depends on it. Release the revision only when those records agree or their exceptions have named owners.
A new chair, sofa or finish may look like a small adjustment. Its dimensions, availability and order identity can make it a broader project change.
Establish the baseline being changed
Use an explicit room and design revision. Retain the previously accepted files and the decision that approved them. If a client comments on an old screenshot, first identify which revision it shows; otherwise a clear request can still be applied to the wrong arrangement.
Planner 5D’s room editing guidance includes controls for managing scene editing.1 Editing controls help protect a scene, but the decision history still needs its own record.
Classify the request
Separate a visual correction from a product substitution, a layout change and a new requirement. A corrected material assignment may leave the order untouched. Replacing the actual material can change its product code, sample approval and price. Ask which of those decisions the requester intends.
| Request | Check dependent records |
|---|---|
| Move a sofa | Plan, door conflicts, views and installation instructions |
| Substitute a finish | Region mapping, sample, finish schedule and order |
| Replace a fixture | Dimensions, technical interfaces, budget and procurement |
| Change a camera | Presentation views; preserve the underlying layout |
Build the affected-file list
Trace the changed item to room plans, renders, finish schedules, FF&E lists, quotations and purchase records. Include external recipients: the purchasing team may be working from an attachment rather than the latest project link.
For each dependency, record whether it needs rebuilding, a metadata update or no change. This avoids regenerating every image while leaving one important schedule untouched. Link the reason for “no change” when the relationship is not obvious.
Obtain the right acknowledgement
Assign a decision owner and a receiving owner. The client can approve appearance while purchasing confirms the revised item and the installer confirms an affected interface. Do not collapse those different questions into a single “approved” checkbox.
Use the substitution guide for the commercial comparison and the presentation handoff for the receiving package. A revised image should point to the same item and finish as the schedule.
Release a coherent revision
Run a small reconciliation: select one changed item, open its current plan, image, schedule and order reference, and compare identities. Record actual discrepancies and correct them before expanding the review to other affected items. This is a protocol to execute, not a claim that your project has already passed it.
The revision worksheet captures the baseline, decision, dependencies and acknowledgement. Retain replaced files as superseded rather than silently overwriting the accepted history. Use the Rendora interior entry for the room workflow and attach the decision record to the resulting handoff.